Viewing 1 post (of 1 total)
  • Author
    Posts
  • #1016

    This weekend they had the cement trucks back on site to finish up the closure strip pour. This pour locks in the Tilt Up Wall rebar structure with the slab/footer rebar system. While this adds a structural component to the tilt up wall, the bracing can’t be removed yet as it needs the structural steel to be installed before it is fully supported from all force vectors.

Viewing 1 post (of 1 total)
  • You must be logged in to reply to this topic.